Transformer Commissioning Procedure
transformer commissioning at site
After the satisfactory completion of installation, the
following pre-commissioning checks, and tests on instruments must be performed
before putting the transformer into service.
COMMISSIONING TESTS
1) Insulation
Resistance (IR)
1a) Before starting this test all the power terminal bushings
should be thoroughly cleaned with a dry clean piece of cloth.
1b) At all the tap positions, IR values of windings to earth
& between windings shall be measured with designated insulation tester of
suitable ratings and readings noted.
Between HV Winding and
Earth (Megger) use 5000V or 2500V Insulation Tester,
Between HV and LV
Winding (Megger) use 5000V or 2500V Insulation Tester,
Between LV Winding and
Earth (Megger) use 1000V or 500V Insulation Tester,
1c) IR values obtained should be similar to those indicated
in the manufacturers’ test report, furnished with the handing –over documents.
In humid weather, IR values obtained may be lower due to condensation on the
terminal bushings
1d) If IR values are very low and unacceptable, and then it
may be necessary to filter the oil / dry-out the winding till the insulation
reaches satisfactory values.
2) Break-Down Voltage
(BDV) Test:
2a) Oil samples from tank bottom, tank top, radiator, etc.
shall be carefully taken and tested for BDV value, as per clause of manual.
2b) BDV value of oil should be more than 50kV (rms) for 1
minute in the standard test cell
2c) If BDV value is very low and unacceptable (30kV(rms) or
less for 1 minute, then it may be necessary to dry-out & clean the oil till
the insulation reaches satisfactory values.
It is recommended to contact suppliers or manufacturer for
suitable recovery procedure based on available facilities at site
3) Voltage Ratio Test
3a) Apply 3-Phase, 433V AC supply on the HV side and the
Voltage Ratio at all tap positions can be derived using suitable precision
voltmeter connected to the LV side. A ratio meter, if available can be used for
a more accurate measurement
3b) The Ratio value obtained should be similar to those
indicated in the manufacturers’ test report, furnished with the handing-over
documents.
4) Winding Resistance
Measurement Test
4a) Winding Resistance of every phase of
each winding should be measured using a suitable DC Resistive Bridge or
similar.
4b) Winding Resistance values obtained
should be similar to those indicated in the manufacturers’ test report,
furnished with handing-over documents
5) Marshalling Box
Scheme Check
5a) All the auxiliary wiring from various accessories to marshalling
box shall be checked with marshalling box scheme drawing furnished with the
handing-over documents.
5b) During testing of accessories like Buchholz relay, etc.,
an operation of all the alarm/trip contacts shall be checked at marshalling box
terminal blocks ensuring both operation and wiring are checked correctly.
6) Buchholz Relay Test
6a) Relay operation for alarm and trip contact shall be
checked by injecting air inside the relay through test petcock. Injected air
collected inside the relay allows the alarm float/flap & trip float/flap to
fall thereby operating their respective switch
7) Temperature Indicator
Test
7a) Indicators operation for alarm and trip contact shall be
checked by manual stimulation
8) Off-Circuit Tap Selector (OCTS)
8a) During shipment, generally, the OCTS has not been
separated from the transformer so it is not necessary to recheck the internal
connections of tapping an internal mechanism
8b) Means of protecting the OCTS from unauthorized operation
is provided by using a padlocking arrangement at the designated tap position
9) Before switching, it is to ensure that
9a) All the Oil Shut-off Valves are OPEN and Draw-Off Valves
are CLOSED.
9b) All Thermometer Pockets are near filled (85%) with oil.
9c) Oil is at the correct level in the Bushings, Conservator,
etc
9e) Earthing Connection of Main Tank, Neutral Bushing,
Marshalling Box, Control Gear Box, Cable Box, Arcing-Horn, etc., are correctly
made.
9f) Bushing arcing horn gap is set correctly
9g) All CT Secondary Circuits are closed
9h) All Air-Release Plugs of Main Tank, Radiator, Conservator,
Buchholz Relay, Bushings, etc., are free of air pocket/bubbles.
9i) It is recommended that after Oil-Filling/filtration or before
Commissioning, at least 10-12 9j) hrs. Should be allowed for the oil to
settle-down and the air is released from all points at 2 hourly intervals.
9k) It is recommended that the transformer is initially
energized at NO-LOAD only and checked for any abnormalities for the next 6 - 8
hours
9l) AFTER SWITCHING on no-load, if the Primary side Circuit
Breaker is tripped investigate the cause thoroughly and re-energize the
transformer ONLY AFTER ensuring that the fault is properly cleared.
9m) If satisfactory (transformer on No-Load) then apply load
gradually and observe for any abnormalities for the next 6- 8 hours
9n) If the transformer is satisfactory on-load up to 50% for
the first 4-8 hours, shut-down the transformer and ensure that all air-release
plugs of the tank, radiator, conservator, Buchholz relay, bushing, etc., are
free of air pockets which might have developed during initial loading.
Credit:
rajasthanpower.in
Thanks for sharing this informative blog.Axis Electricals offers diverse cable lugs and connectors, ensuring secure, robust, and conductive connections. Shop now for high-quality supplies!
ReplyDeleteVisit:
lugs manufacturers in india