Pre Monsoon Electrical Checklist
Location:                                                                                                    date:
Sr.
Description
Locations
requiring
improvements
Action required
Action by
Target
1
Surrounding drain of substation /control room is clear.




2
Drain pipe is clear




3
Cable entry is sealed properly




4
Window panes are ok and intact.




5
Marshalling box of transformer is closed properly




6
Soak pit is clean if any




7
Do temporary electrical panels have
 sheds?




8
Whether all the GI.sheet made sheds   
 are tightly secured?




9
Is drainage around temporary panels  
 Adequate?




10
Has RCCB /ELCB been provided for         
 all the connections of Electrical tools                    
and lights?




11
Gum boot/raincoat/umbrella available with working manpower




12
Sufficient Terpolene is available for handling emergency power




13
JB of surround area is closed




14
De-watering pump is available of sufficient capacity




15
Surface area is even/plane to pass water.





Other findings ---











Inspected By):                                                                    reviewed by:
               
               

2 comments:

  1. We are engaged to offering Mansoon sheds with manufacturing, supplying, exporter and trading. We have designed and develop Mansoon sheds exclusive range as per the industry standards and in different specifications.
    Visit us on: http://www.shreetarpaulins.com

    ReplyDelete

SOP, Standard Operating Procedures

  1.1 .    Definition SOP is termed commonly as Standard Operating Procedures- SOP  Characteristics of SOP- 1)     Carry out the operati...